Procedure for Wall Tiling Preparatory work before tiling: Note that all electrical and plumbing wall chasing works for the concealed piping, bore holes etc. is complete before starting of wall tiling. Rough coat plaster : Rough coat plaster or first coat plastering for walls including corners has…

Procedure for Wall Tiling

Preparatory work before tiling :

  • Note that all electrical and plumbing wall chasing works for the concealed piping, bore holes etc. is complete before starting of wall tiling.
  • Rough coat plaster : Rough coat plaster or first coat plastering for walls including corners has neatly finished with line, level, right angles and plumb.
  • For proper bonding of wall tiling, wave lines markings to be done using binding wire over this plastered surface.
  • It is highly advisable to start the rough coat plaster for walls after a completion period of 28 days of masonry walls constructed in block work or brick work.
  • Similarly, the glazed tile, wall tiling or ceramic tiling work can start only after completion of 28 days of rough plastering, to facilitate shrinkage of plaster.

Fixing of Wall tiling :

  • Cutting of tiles : Proper planning and care is required while cutting of tiles, so that the wastage can be minimized.
  • The Cut tiles can be used for internal corners, and other places where full tile is not required.
  • Ensure the distance from the skirting board or worktop to the top of the panel is fixed first only with full tiles, so that to facilitate the grouting gap.
  • After the adhesive is allowed to dry, the border or edge tiles can easily be fixed over the wall.
  • All Tiles are to be soaked in water for at least two hours before its use.

Wall tiling work :

  • A cement paste with good consistency is applied on the back of the tile impressed on to the background surface and tapped mildly with a wooden or rubber mallet.
  • Wall tiling work is done by fixing joints of 2.5 mm between tiles. To get uniform joint width in all directions, spacers of reputed brand is advisable.
  • Proper skill, observation is required to keep all tiles perfectly in horizontal and vertical direction.
  • By holding straight edge for horizontal lines, plumb bob for verticality, spirit level for top level, the required parameters can be achieved as per standards.
  • Corner beads : All wall tiling corners to be provided with reputed PVC tile corner beading or strips so that tiling can be commenced beyond the beading.
  • Shrink free : All joints to be filled with a branded non-shrink waterproofing filler material called shrink free of matching colour giving a minimum duration of 24 hours and finished slightly sunken.

Inspection Procedure for Quality Assurance :

  • Check all tiles before its laying with MTC, random test reports by third party for its dimensions, durability, hardness, scratch proof etc.
  • Grout colour : Ensure conformance of the wall tiling pattern, specifications including tile grout colour are as per drawings.
  • Check for uniformity in line, level and grout thickness for visual appearance.
  • Ensure straightness and level of wall tiling surface.
  • Tile fixing : The fresh tiled surface should exhibit proper level by using Aluminium straight edge or line thread and spirit level or level tube for maintaining top level.
  • Make sure, the cement and the sand have been checked or tested before starting of wall tiling
  • Ensure that no tile is broken, damaged or cracked and the joints are well filled.
  • Randomly, tap the tiled surface to check for hollowness.
  • The tiled surface should covered with POP or tile protection sheets of reputed brand against damage to the tiled surface.

Wall tiling in progress

Bottom layer of wall tiling in progress

Corner beading for tile edges

Wall tiling completion

Share on facebook
Facebook
Share on whatsapp
WhatsApp
Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on pinterest
Pinterest

Myhome

• I Have 28 Years of Vast experience in the field of construction backing with Civil Engineering Degree from Recognized University and College. Also done PMC, Member of Institute of Engineers and Registered Engineer in BBMP. • Have worked with many Reputed Builders, Contractors and MNC’s and moreover ran Own Construction Company. • Have Rose from Site Engineer to GM, Quality Head, Consultant and Managing Partner in the said company. • I Have expertise in various kinds of Constructions including Residential, Commercial and Industrial and well versed with ISO standards for Quality, Environmental and OSHAS • I have done/doing construction audits, observations, actions taken and improvements, for many reputed companies. • I do Training and Development for all Engineers

Leave a Reply

Close Menu